Water & Sewer Project Construction Update Feb 9, 2023



Teresa Irby-Butler provided a construction update to the American Beach Water & Sewer Advisory Board at the February meeting.


ACHIEVEMENTS OVER THE LAST 30 DAYS:

  • Gopher Tortoise relocation (only 3 tortoises found vs expected >14 represents a good saving of money)

  • Underground subcontractor mobilized

  • Traffic detours established (pedestrian detours coming soon)

  • Phase 1 structures delivered - manholes, lift stations etc.

  • Phase 1 road milled

  • Silt fencing installed

  • De-watering installed and operating


(Images top to bottom and left to right)

1) First Manhole

2) Dewatering Pipes

3) Lewis Street Beach Access

4) Filtered discharge from dewatering pipes

5) Manholes for the project

6) Drop manhole

7) Surveying markers - PLEASE DON'T TOUCH!!

8) Gopher Turtle removals - only 3 vs more than 14 in the budget.



CONSTRUCTION OVER THE NEXT 30 DAYS

  • Relocate water main

  • Run pipes:

  1. south on Gregg

  2. round Burney

  3. along Ocean

  4. on North side of Gregg


Projected Road Closures



Funding application

We appear to be in a good position with regard to the REDI grant application - the project meets the core mission of the granting agency and very importantly, showed a greater than 50% participation from the community.


NEXT STEPS:

  1. Grant application for $992,000 was submitted on January 29, 2023

  2. St John's River Water Management will review

  3. Grant selections will be approved April 11th

  4. Grant agreement negotiated and approved May - October

  5. Negotiate Plumber's scope, May - October

  6. Obtain Property Access Agreements, May - October ****

  7. Commence tank abandonment no sooner than October


**** Teresa Irby-Butler has asked the community to be aware that property owners be aware that they will be asked to sign a form allowing plumbers onto their property to conduct the necessary survey for the tie-in work.