
Current status of the project:
Construction Activities Last 30 days
• Completed installation of all 22 manholes in Phase I
• Completed installation of Phase I 8”sewer main
• Installed 1st watermain loop
• Completed sewer laterals, 2 outstanding
Construction Activities Next 30 days
• Pressure test, flush and connect 1st water section
• Cast inverts for Phase I
• CCTV inspection of Phase I sewer main
• Clear at LS#1
• Phase I subbase in July
• Commence force main installation
Current Construction Schedule
• ~3 1⁄2 months behind schedule
• Projected completion date April-May ‘24 versus Jan ‘24
Delays
• Unknown utilities
• Gopher tortoises
• Supply Chain delays
Schedule Recovery
• 2 crews/3rd crew mobilize next week
• Increased production
• SRF amended to align with construction duration
Phase 1 Sewer Outstanding Work Activities
• Complete lateral installations @5577 Gregg & 95570 Burney
• Set lift station LS#2 (to be coordinated with setting of LS#1)
• Install pumps, piping, electrical
• Construction sewer transmission forcemain
• Test & inspection system
• Pressure test sewer main and forcemain
• CCTV inspection of mains
• Hydraulic test of lift station
Phase 1 Water Outstanding Work Activities
• Various sections to be placed into service
• Complete installation of water mains
• Complete installation water laterals to edge of ROW
• Continue installation fire hydrants
• Test & inspection system
• Pressure test water main
• Disinfect & BACT test water distribution system
REDI Grant Next Steps
• Grant application submitted Jan 29th
• Grant selections approved April 11th
• Negotiate statement of work June 1st
• County approve grant agreement TBD
• Release bid for plumber’s scope July
• Execute plumber ’s contract Oct
• Execute agreement with SJRWMD Oct
• Obtain Property Access Agreements
for Permitted & Expected Septic tanks* July-August ‘25
• Commence tank abandonments TBD
• Complete work within 2 years September ‘25
**REDI Grant Work Access Agreements provide temporary legal access to private property as needed to:
• Decommission existing septic tank and drainfield in place
• Construct new sewer service lateral
• Connect new lateral to new sewer collection system located at edge of ROW
Click on the image below for the full presentation with maps etc.
Links to previous updates: